Our Story · Assa, Imo State · March 2026

Building Nigeria's
energy future
from the source.

ANOH Energy Hub is not a concept. The site is secured, the gas is allocated, the engineering is complete, and the team that will deliver it has done it before — at the highest levels of Nigeria's oil and gas industry.

Why ANOH. Why now.

Southeast Nigeria sits on one of the country's richest gas deposits — yet its factories run on diesel, its hotels run on diesel, and its communities have among the worst power access in the nation. The North is no better: five states with significant industrial demand and zero gas pipeline infrastructure.

Gulf of Guinea Midstream Limited was formed to close that gap. Not with a pipeline that would take a decade to build — but with a strategically located hub that can compress gas into CNG for the South and liquefy it for the North, from a single site 1.5 km from Nigeria's most modern gas processing facility.

ANOH Energy Hub is the result: a first-of-its-kind integrated dual-fuel platform with secured gas, secured land, completed engineering, and five open partnership roles waiting to be filled.

30MMscfd
Gas allocation secured from AGPC — Nigeria's most modern processing plant
13.5ha
Site fully acquired — 230 plots, RoW compensation paid, physical possession achieved
100%
Engineering complete — P&IDs, PFDs, equipment specifications, pipeline design
Jan '27
First Gas target — NTP imminent, compressor on order, GSPA negotiations active

Nigeria's most modern gas plant. 1.5 km away.

The Anoh Gas Processing Company (AGPC) facility is Nigeria's newest and most advanced gas processing plant — built to international standards with significant throughput capacity. ANOH Energy Hub sits 1.5 km away, connected by a direct 8-inch API 5L X60 spur pipeline.

This proximity gives ANOH an unmatched supply security advantage that no other CNG or LNG operator in Southeast Nigeria can replicate. The gas flows reliably. The pressure is right. The quality is certified.

Pipeline tie-in
1.5 km · 8-inch API 5L X60
Inlet pressure
94 barg
Feed gas composition
CH₄ 85.76% · Zero H₂S
HoT status
Signed with AGPC
Satellite view — ANOH CNG Park Site and AGPC Processing Plant, 1.5km apart, Assa, Imo State
ANOH Park Site → AGPC Plant: 1.5 km
Assa North, Ohaji/Egbema LGA, Imo State

The site is ready.
The work has begun.

Land title & acquisition
All 7 landowner purchase agreements executed. 230 plots (13.5 ha) in Umuepe, Assa North LGA.
Complete
Right-of-Way compensation
Full RoW compensation paid to all affected landowners. Pipeline corridor of 1.5 km cleared and graded by March 2026.
Complete
Physical site possession
Full physical possession achieved. Site cleared. Heavy equipment mobilised. Contractor (PAULASH Kegoz Construction) engaged.
Complete
Engineering design
100% complete. P&IDs (12 sheets), PFDs, heat balance, mechanical equipment list, civil/structural, utility systems — all finalised.
Complete
Access road construction
Site access road construction underway. Progress: 60% as of March 2026.
In Progress
Regulatory permits
NMDPRA Gas Transmission Licence application submitted. EIA/Environmental Permit in progress. Land Title Perfection 80% complete.
In Progress
13.5ha
Site area secured
230 plots · Umuepe, Assa North LGA, Imo State · Fully acquired
4,458
Plant footprint
Designed for 50 MMscfd full capacity · Phase 1 targets 2 MMscfd fixed
1.5km
Pipeline to AGPC
8-inch API 5L X60 · ROW corridor cleared · Tie-in to 36-inch NGC trunk line
7
Landowner agreements
All executed and paid · Survey stakes placed · No outstanding land claims

From concept
to First Gas.

Q4 2025 — Complete
Engineering & Site Preparation
100% detailed engineering complete. P&IDs, PFDs, equipment specifications finalised. Site cleared, RoW secured, pipeline corridor cleared. HoT signed with AGPC.
Q1 2026 — Complete
Land, RoW & Commercial Frameworks
All 7 landowner agreements executed. Full RoW compensation paid. GSPA negotiations active with AGPC. Gas transmission licence application submitted to NMDPRA.
Q2 2026 — Current
Partner Close & FID
Partnership roles being filled. Financial close targeted. NTP to be issued to Celsara Nigeria upon funding close. Long-lead equipment orders to be placed immediately.
4
Q2–Q4 2026 — Upcoming
Construction & Commissioning
Civil works, 1.5km pipeline construction, AGPC hot-tap tie-in, compressor installation, mobile skid deployment, tube-skid truck activation.
January 2027 — Target
First Gas & Commercial Operations
First gas introduction to fixed facility. Performance testing and validation. Commercial operations commence across CNG, LNG, and power streams simultaneously.

The team that delivers.

Nze Joe Ibeh
CEO & Lead Director · FNMGS Certified
Nze Joe Ibeh
Fellow, Nigerian Mining and Geosciences Society
36+ years Oil & Gas leadership expertise across upstream, midstream and downstream
Nigeria's OPEC Representative (2005–2007) · OPEC Economic Commission Board Member
Former Executive Director, NPDC Operations
Former Executive Director, NNPC London
Infrastructure deal structuring specialist
Strategic Value
Critical NNPC/DPR relationship management, gas supply security negotiations, and deep upstream track record that opens doors no other team can access.
Athiel Greenidge
Director
Athiel Greenidge
Nigerian market experience since 1984. PSL Engineering founder. Midstream operations specialist.
Capital sourcing & Ops
Prof. Ayo Olajuyigbe
Sustainability
Prof. Ayo Olajuyigbe
Chief Sustainability & Planning Officer. PhD Urban Planning. ANOH CNG Park EIA/ESIA specialist.
Govt approvals & ESG
Cynthia Tishion
Governance
Cynthia Tishion
Board Member & Legal Advisor. Corporate Governance Expert. Gateway to Nigeria's Energy Future.
Legal & compliance
Adegoke O. Wonuola
Director
Adegoke O. Wonuola
Astute Marketing Executive. 18 years quality & value driven experience. Business development in Free Zones.
Marketing & Biz Dev
Frank Hamilton
Technical Adviser
Frank Hamilton
LNG industry expert. Former Chart Industries Senior Principal. Director & Technical Adviser.
Technical design & risk

Regulatory pathway
well advanced.

NMDPRA
Gas Transmission Licence
Required for gas transportation and compression operations
FMENV / NEPZA
Environmental Permit (EIA)
World Bank ESF-compliant EIA completed by Prof. Olajuyigbe
In Progress
Imo State LTE
Land Title Perfection
Certificate of Occupancy process at 80% completion
80% Complete
FIRS
Tax Clearance Certificate
Current and valid for all corporate entities
Valid · Current
NUPRC
Marginal Field Licence
Existing licence covering the project area
Existing · Valid
NERC
Generation Licence (IPP)
Required for power plant partner — pathway supported by GGML
Partner Supported

Ready to explore a
partnership role?

View All Five Roles → Request a Briefing